Installation & Operation Manual
Models: 1.0 - 1.3 - 1.5
This manual must only be used by
a qualified heating installer / service
technician. Read all instructions,
including this manual and the SYNC
Service Manual, before installing.
Perform steps in the order given.
Failure to comply could result in
severe personal injury, death, or
substantial property damage.
WARNING
Save this manual for future reference.
SYNC-I-O Rev I
Seitenansicht 0
1 2 3 4 5 6 ... 67 68

Inhaltsverzeichnis

Seite 1 - Models: 1.0 - 1.3 - 1.5

Installation & Operation ManualModels: 1.0 - 1.3 - 1.5This manual must only be used by a qualified heating installer / service technician. Read

Seite 2 - Hazard definitions

Installation & Operation Manual10Products to avoid:Spray cans containing chloro/fluorocarbonsPermanent wave solutionsChlorinated waxes/cle

Seite 3 - Please read before proceeding

Installation & Operation Manual1 Determine boiler location (continued)11When removing a boiler from existing common vent system:Do not in

Seite 4 - The SYNC - How it works

1 Determine boiler location12 Installation & Operation ManualCombustion and ventilation air requirements for appliances drawing air from t

Seite 5 - Models 1.0 - 1.3 - 1.5

13Figure 1-7_Combustion Air from Outside - Single Opening4. If a single combustion air opening is provided to bring combustion air in directly from

Seite 6 - Other Specifications

14 Installation & Operation ManualPVC/CPVC Two PipeSee Figure 3-1AStainless Steel Two PipeSee Figure 3-2Direct venting options - Sidewall Vent

Seite 7

15 Installation & Operation Manual2 General venting (continued) Vertical Vent Optional Room AirPVC/CPVCRoom AirSee Figure 4-5Stainless Steel

Seite 8

16PVC/CPVCVertical Vent, Sidewall AirStainless SteelVertical Vent, Sidewall AirDirect venting options - Vertical Vent, Sidewall Air2 General venting

Seite 9 - Vent and air piping

17 Installation & Operation Manual2 General venting (continued)PVC/CPVC vent piping materialsUse only the materials listed in Table 2A on

Seite 10 - 1 Determine boiler location

18 Installation & Operation ManualPVC/CPVC air intake/vent connections1. Combustion Air Intake Connector (FIG. 2-2) - Used to provide com

Seite 11 - (continued)

19Requirements for installation in Canada1. Installations must be made with a vent pipe system certified to ULC-S636. IPEX is an approved vent man

Seite 12

2ContentsHazard definitionsThe following defined terms are used throughout this manual to bring attention to the presence of hazards of various risk l

Seite 13

20 Installation & Operation ManualStainless steel air intake/vent connections1. Combustion Air Intake Connector (FIG. 2-3) - Used to provi

Seite 14 - 2 General venting

21 Installation & Operation ManualVent, air piping and termination:The SYNC vent and air piping can be installed through the roof or through

Seite 15 - General venting (continued)

Installation & Operation Manual3 Sidewall direct ventingVent/air termination – sidewallFollow instructions below when determining vent loc

Seite 16

23 Installation & Operation Manual3 Sidewall direct venting (continued) Vent/air termination – sidewall 5. Maintain clearances as shown in

Seite 17

24 Installation & Operation Manual3 Sidewall direct venting VENT PIPINGGALVANIZEDTHIMBLEVENT CAPAIR PIPINGWALL PLATEVENT PLATEFigure 3-4A S

Seite 18

25 Installation & Operation Manual3 Sidewall direct venting (continued) Termination and fittings1. The air termination coupling must

Seite 19

26 Installation & Operation Manual4 Vertical direct venting Vent/air termination – vertical Prepare roof penetrations1. Air pipe penetrat

Seite 20

27 Installation & Operation Manual4 Vertical direct venting (continued) Multiple vent/air terminations1. When terminating multiple SYNC

Seite 21

28 Installation & Operation Manual5 Hydronic pipingSystem water piping methodsThe SYNC is designed to function in a closed loop pressurize

Seite 22 - 3 Sidewall direct venting

Installation & Operation ManualCirculator sizingThe SYNC heat exchanger does have a pressure drop, which must be considered in your system

Seite 23 - Model Kit Number Vent Size

Installation & Operation ManualPlease read before proceedingInstaller – Read all instructions, including this manual and the SYNC Service Ma

Seite 24

30 Installation & Operation ManualFigure 5-3 Pump Configuration 5 Hydronic piping Hot Water Generator pump sizingThe SYNC has two (2) h

Seite 25 - Termination and fittings

Installation & Operation ManualIt is required that near boiler piping systems utilize Primary/Secondary configurations as shown in FIG.

Seite 26 - 4 Vertical direct venting

32 Installation & Operation Manual5 Hydronic piping HOT WATER GENERATOR SYSTEMCIRCULATOR AIR SEPERATORMAKE UP WATERDRAIN POINT (

Seite 27 - Room air

33 Installation & Operation ManualHOT WATER GENERATOR SYSTEMCIRCULATOR AIR SEPARATORMAKE UP WATERDRAIN POINT (TYPICAL)SYSTEM SUPP

Seite 28 - 5 Hydronic piping

34 Installation & Operation Manual6 Gas connectionsConnecting gas supply piping1. Refer to FIG. 6-1 to pipe gas to the boiler. a. Insta

Seite 29 - Circulator sizing

35 Installation & Operation Manual6 Gas connections (continued) Use two wrenches when tightening gas piping at boiler (FIG. 6-2), using

Seite 30

36 Installation & Operation ManualTable 6A Natural Gas Pipe Size ChartThe gas piping must be sized for the proper flow and length of pipe,

Seite 31 - Near boiler piping components

37 Installation & Operation Manual WARNINGDo not check for gas leaks with an open flame -- use the bubble test. Failure to use the bubble

Seite 32

Installation & Operation Manual7 Field wiring ELECTRICAL SHOCK HAZARD – For your safety, turn off electrical power supply before making a

Seite 33

39 Installation & Operation ManualLow voltage connections 1. Route all low voltage wires through the knockouts in the rear of the boiler,

Seite 34 - 6 Gas connections

Installation & Operation Manual4The SYNC - How it works...1. Access cover - front Provides access to the gas train and the heat exchanger.

Seite 35 - PREVENT PIPE FROM ROTATING

40 Installation & Operation Manual7 Field wiring System supply sensor1. By installing the system supply sensor into the supply of the

Seite 36

41 Installation & Operation Manual7 Field wiring (continued) 1 ALARMLBL20052 REV B30 SHIELD GNDMOD BUS0 - 10V INPUT2 CONTACTS3 RUN

Seite 37 - Gas valve replacement

42 Installation & Operation Manual8 Condensate disposalCondensate drain1. This boiler is a high efficiency appliance that produces conden

Seite 38 - 7 Field wiring

43 Installation & Operation Manual9 Start-upCheck/control water chemistryDo not use petroleum-based cleaning or sealing compounds in the b

Seite 39

44 Installation & Operation Manual9 Start-up Check for gas leaksBefore starting the boiler, and during initial operation, smell near the

Seite 40

45 Installation & Operation Manual9 Start-up (continued) Final checks before starting the boiler Read the SYNC Service Manual to famil

Seite 41 - 7 Field wiring (continued)

46 Installation & Operation ManualFOR YOUR SAFETY READ BEFORE OPERATINGWARNING: If you do not follow these instructions exactly, a fire or

Seite 42 - 8 Condensate disposal

47 Installation & Operation Manual9 Start-up (continued) Check flame and combustion (continued)4. Navigate to the Service Mode Screen f

Seite 43 - 9 Start-up

48 Installation & Operation Manual6. If no other changes are necessary, press the BACK button to return to the Parameter List Screen. 7

Seite 44

49 Installation & Operation ManualGeneralHow the boiler operatesThe SYNC uses advanced stainless steel heat exchangers and electronic contr

Seite 45 - 9 Start-up (continued)

Installation & Operation Manual22438974133363937243222241.0 Model Only2520Left Side (inside unit) 62352614241529Right Side (inside unit) The

Seite 46

10 Operating information50 Installation & Operation ManualGradient limitingIf during operation of the boiler the outlet water temperature

Seite 47

51 Installation & Operation Manual10 Operating information (continued) Monitor external limitsConnections are provided on the connection

Seite 48

10 Operating information52 Installation & Operation ManualIf the water temperature at the system supply sensor is less than the set point

Seite 49 - 10 Operating information

10 Operating information (continued)53 Installation & Operation ManualSequence of operation1.Upon a call for heat, the control turns on th

Seite 50

10 Operating information54 Installation & Operation ManualSYNC control moduleFigure 10-1 Status ScreenThe Status Screen displays boiler st

Seite 51 - Boiler temperature regulation

10 Operating information (continued)55 Installation & Operation ManualBoiler Configuration - This line shows the current configuration of

Seite 52

56 Installation & Operation Manual10 Operating information Figure 10-2 Main Menu ScreenUse the Main Menu Screen (FIG. 10-2) to access the

Seite 53 - Sequence of operation

57 Installation & Operation Manual11 Maintenance Maintenance and annual startupTable 11A Service and Maintenance SchedulesService technici

Seite 54

58 Installation & Operation Manual11 Maintenance Follow the service and maintenance procedures given throughout this manual and in compo

Seite 55

59 Installation & Operation Manual11 Maintenance (continued) Flue vent system and air piping1. Visually inspect the entire flue gas vent

Seite 56

6 Installation & Operation ManualRatingsSYNCI=B=R RatingModel NumberNote: Change “N” to “L” for L.P. gas models.InputMBH(Note 4)

Seite 57 - 11 Maintenance

60Check flame signal1. At high fire the flame signal shown on the display should be at least 10 microamps.2. A lower flame signal may indicate a fou

Seite 58

61 Installation & Operation Manual11 Maintenance (continued) The boiler contains ceramic fiber materials. Use care when handling these ma

Seite 59 - 11 Maintenance (continued)

62 Installation & Operation Manual11 Maintenance Handling ceramic fiber materialsREMOVAL OF COMBUSTION CHAMBER LININGThe combustion chambe

Seite 60

63BOX DEPICTSOPTIONAL ITEMSLADDER DIAGRAMLBL20058 REV ECONTROLMODULE 2X5-3X2-1GAS VALVEGAS VALVERELAYX5-5X5-13X5-6X5-121245TR1X1-7FLAME RODSPARKROD120

Seite 61

64 Installation & Operation Manual12 Diagrams Figure 12-2 Ladder Diagram_Part 2BOX DEPICTSOPTIONAL ITEMS120 VAC24 VAC120VACTERMINAL STRIP

Seite 62

Installation & Operation Manual12 Diagrams (continued) Figure 12-3 Wiring DiagramBOX DEPICTSOPTIONAL ITEMSOUTLETSENSORNotes:1. All wirin

Seite 64

67Notes

Seite 65 - 12 Diagrams (continued)

Revision Notes: Revision A (ECO #C02428) initial release.Revision B (ECO #C03046) reflects the addition of FIG. 5-3 on page 27, the addition of a pre

Seite 66

7 Installation & Operation ManualInstallation must comply with:• Local, state, provincial, and national codes, laws, regulations, and ordi

Seite 67

Installation & Operation Manual86"(152 40 MM)24" (610 MM)REAR0"LEFTOPEN FRONT13" (330 MM)TOP0"RIGHT1/4” (6 MM) MI

Seite 68

Installation & Operation Manual91 Determine boiler location (continued)Provide air openings to room:The SYNC alone in boiler room1. No a